1.Create inspection plan for material.
2.assign all material and vendor to task list counter.
3.T code QP02 go to overview screen select MIC and click on dependent characteristic
system will pop up screen here, add vendor and maintain vendore wise specification for MIC Selected.
4.When GR will be taken against vendor, system will generate inspection lot, lot will have specification of MIC as per Vendor.