For Complete set up procedure refer below link.
http://www.erpbizz.com/MM/Release-Strategy.htm
Release
strategy setting for PO or PR Consist 2 levels.
1. Set up Release Procedure
It includes
creation of release code and mapping sequence of release code in order to get
release strategy.
Change in
release indicator should happen after last release till then it should be in
blocked status.
e.g.. below
release strategy no 3 consists 4 levels so up to level third release indicator
should be blocked stage however after getting released by last release code
i.e. V3 release indicator should change to “ I ” i.e. Released.
Caution -
If there are some changes required in existing release strategy related to
shuffling or adding or deletion of release code.
it is
advisable to create new release strategy for these changes because changing in
existing release strategy would also change existing released PO
levels also.
2. Value Assignments
As u may
aware that for assignment purpose we need to create one class with class type
032 and some controlling characteristics
in below
case release strategy will be trigged on combination of PO Doc Type,PO Value, Pur
Grup and Plant.
so all 4
created as characteristics and assigned to class type PO-Class.
Rel Strat |
Release Levels |
PO Doc Assigned |
Value Assigned |
Buyer Code |
Plant |
|
|
|
|
|
|
1 |
SM- Area manager |
NB1- Raw Material |
0-10000 INR |
P1-
N Tiwari |
1280 |
|
FI Accounts Dept |
NB2-Spare Purchase |
|
|
|
|
|
|
|
|
|
2 |
SM- Area manager |
NB1- Raw Material |
10000.01 - 25000 INR |
P1-
N Tiwari |
1280 |
|
FI Accounts Dept |
NB2-Spare Purchase |
|
|
|
|
V2 Vice President |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3 |
SM- Area manager |
NB1- Raw Material |
> 25000.01 INR |
P1-
N Tiwari |
1280 |
|
FI Accounts Dept |
NB2-Spare Purchase |
|
|
|
|
V2 Vice President |
|
|
|
|
|
V3 CEO |
|
|
|
|
|
|
|
|
|
|
Read more...